Accessing CSX property for any purpose requires permission. Any construction requires plan review, flagging and/or inspection, scheduling, and a signed Agreement from CSX. Safety is our overarching concern.
Utility Permits: Utilities that go over, across, or under the railroad tracks or CSX property. See separate section below for longitudinal occupancies (i.e. utilities paralleling tracks).
- Wirelines – Electrical, Fiber, Cable, etc.
- Pipelines – Water, Sewer, Gas, culverts, etc.
- Small cell construction (complete the new Utility Application)
Rights of Entry Permits: Right of Entry access for temporary purposes ONLY.
- Surveying, Ingress/Egress, Inspection of bridges, roads, soil borings or sampling, wide load on operating track and/or property, and property remediation.
- Environmental investigation, monitoring wells, soil testing, etc.
Wireless Infrastructure Permits: The construction of new or co-location of wireless equipment on CSX property.
- New tower construction
- Co-location on existing CSX structures or third party structures
- Modifications to existing towers
Longitudinal Occupancy Permits: The construction of new utilities that run alongside (i.e. parallel) the railroad tracks and/or CSX property.
- Wirelines – Electrical, Fiber, Cable, etc.
- Pipelines – Water, Sewer, Gas, Culverts, etc.